| Facilities/Safety Committee Agenda |
MINUTES |
| I. |
Call To Order |
6:06 PM |
| II. |
Approval of Minutes |
Approved |
| III. |
Old Business: (The following items are all updates): |
|
| |
A. Stadium Turf Replacement |
Replacement is going well
90% complete
200-250 Tons of Sand Crumb were applied
Northeast corner needs repairs
Final walk thru is scheduled for July 23, 2026 with Mr. Fluke and Dr. Wiestling
New turf is guaranteed for 12-14 years |
| |
B. Stadium Scoreboard |
New scoreboard is to be shipped on July 15, 2026
Replacement will take place August 10, 2026
Cost coming out of Capital Reserve will be $15,500
Strickler Signs is the company the turf was bidded to |
| |
C. Natatorium Pool Water Heater |
Order has been placed
Scheduled for July 31, 2026 - Not installed |
| |
D. Gates at the Middle School |
Waiting on installation
Needs fabrication |
| |
E. Stages at High School and Middle School |
Problems occurred
Waiting on scheduling due to other schools having their stages checked
Need to have patience |
| |
F. Facilities Grant |
No additional information at this time |
| |
G. North Salem Elementary Stormwater Management Plan |
Received responses from Dover Township
Post Construction Management Plan
Gordon L. Brown is in charge of this issue
Waiting on a response |
| IV. |
New Business: |
|
| |
A. High School Turf Field Fence |
Upper end of Soccer/LaCrosse Field
Fence is 16 feet high and 80 feet long
Fence is cupped away possibly form the wind but uncertain
Needs replaced due to being a safety issue |
| |
|
Another section that is a safety issue
Southwest Side needs repaired as well
Could reuse material
Fence is not touching post
Expense for this will come out of Capital Reserve
Mr. Fluke will supply pictures |
| |
B. Dishwashers at Leib and North Salem |
All parts are obsolete
Ms. Renard received quotes
Lowest bid was selected
Purchasing cost will come out of Food Service Fund
Leib Elementary Cost $52,539.30
North Salem Elementary $70,499.30 |
| V. |
Business or Comments from Administrators |
|
| VI. |
Business or Comments from Board Members |
|
| VII. |
Public Comment |
|
| VIII. |
Next Meeting: August 11, 2026 |
|
| IX. |
Adjournment |