V. NEW MIDDLE SCHOOL
Description:
The purpose of this agenda item is to provide an update on the finances for the Middle School project.
|
|
V.A. Projected Project Balance
Description:
The purpose of this agenda item is to provide an update to the committee on the financial status of the Middle School project. Admin will share a high level estimate of the additional project savings.
i. Current contract value: $87,355,973 ii. Final contact value: $82,120,000
i. Breakdown of savings:
|
|
V.B. Middle School Track
Description:
The purpose of this agenda item is to review options for the middle school track. The original project plan was to apply a high quality rubber coating to the top of the existing track. Upon evaluation, the selected vendor believes the rubber surface will have a limited lifespan due to the age of the original track base. Vogel has presented the following options:
Option 1: Patching, crack fill, seal coat and re-stripe
Option 2: Mill and overlay
Option 3: Demolish Track, repair base rock, and rebuild
Add Option 4: Apply rubber track surface on top of new pavement
Notes:
|
|
V.C. Classroom Safety Enhancements
Description:
The purpose of this agenda item is to review the options for classroom safety enhancements at the new middle school. The board has previously seen two options. Dustin Lybeck has researched the two options and would like to present a recommendation. Dustin will be present to discuss this option.
Attachments:
()
|
|
VI. APPROVAL OF CAPITAL MAINTENANCE REQUESTS
Description:
The purpose of this agenda item is to review our standard agenda item for district-wide capital maintenance requests. Attached please find the capital maintenance tracking spreadsheet for July. Administration will review the maintenance tracking spreadsheet regarding funds available for capital maintenance requests.
Also attached, please find the capital maintenance project log for summer 2026. The School Board has approved a 2026-27 budget of $1 million. |
|
VI.A. Update on Summer Projects
Description:
The purpose of this agenda item is to provide an update on the 2026 summer projects. As a reminder, the board approved a $1 million capital projects budget.
Attachments:
()
|
|
VI.B. Potential Future Projects and Need for Additional Funding
Description:
As indicated in the above agenda item, we are close to using the entire $1 million in capital maintenance funds for the 2026-27 school year. Administration is requesting consideration of an additional $250,000 for the attached projects. The $250,000 would be allocated from the new middle school project savings. John Cramer will be present to discuss these projects.
Attachments:
()
|
|
VII. NOVEMBER 2026 CAPITAL REFERENDUM
Description:
Attached please find the initial proposal from Rettler regarding the creation of a capital project prioritization list for the outdoor athletic facilities. We have requested several modifications to this agreement and will have an update at the meeting.
Please see the attachment for the response from Rettler in regards to administrative requests. Responses are in blue on page 2.
Attachments:
()
|
|
VIII. FUTURE MEETINGS
|
|
IX. ADJOURN
|