January 6, 2015 at 6:00 PM - Finance & Facilities Committee
Agenda |
---|
1. Welcome and Introduction
|
2. Capital Projects
|
2.1. Review of Project Planning
Attachments:
(
)
|
2.2. List of Known Items Currently Not Scheduled (updated list)
Attachments:
(
)
|
3. Old Business (follow up from December)
|
3.1. ROHS Restrooms
|
3.2. FEMA/Flood Updates
|
3.3. ROHS Auditorium
Attachments:
(
)
|
3.4. Bleacher Inspection Reports
Attachments:
(
)
|
4. Summer 2015 Projects
|
4.1. Asbestos Abatement Contract Recommendation
Attachments:
(
)
|
4.2. Demolition Contract Recommendation
Attachments:
(
)
|
4.3. ROHS Lockers and Painting/Addams Painting
|
4.4. Barton Malow Contract Amendment/Extension Recommendation
Attachments:
(
)
|
4.5. Addams Door Project
|
5. Technology Projects
|
5.1. Current
|
5.2. Summer 2015 Video Surveillance Projects
|
6. Audit Contract Extension Recommendation
Attachments:
(
)
|
7. Other Items
|
8. Opportunity for Citizens to Speak
|
9. Next Meeting: February 5, 2015, 6:00 p.m.; Location: 800 DeVillen
|
10. Adjournment
|