January 30, 2025 at 7:30 AM - Projects Committee Meeting
Agenda | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
1. UNFINISHED BUSINESS
|
||||||||||
1.A. Committee Chair Election
Rationale:
A new Projects Chairman and Vice Chairman need to be elected.
|
||||||||||
2. SWCP
Rationale:
Attached is current SWCP policy that will need to be modified/approved as needed.
Attachments:
(
)
|
||||||||||
2.A. SWCP Application Approvals
|
||||||||||
2.B. SWCP Payments
|
||||||||||
2.C. SWCP Cancellations
|
||||||||||
2.D. Wahoo Creek Cost Share Approvals
|
||||||||||
3. JOINT WATER MANAGEMENT ADVISORY BOARD (JWMAB)
Rationale:
The next JWMAB meeting is scheduled for January 30th, agenda is attached. Due to overlap with other committees, staff will take notes and send them to Directors in Dodge County.
Attachments:
(
)
|
||||||||||
3.A. East Fremont/Elkhorn Township Drainage - FEMA HMPG
|
||||||||||
3.B. West Fremont - FEMA BRIC
|
||||||||||
3.C. Rawhide Creek Watershed - NRCS WFPO
Rationale:
The following is an estimated schedule for the remaining plan milestones:
It is expected that we can request (get in line for) design funds later this summer. Even though design is 100% paid for by NRCS, it is recommended that an MOU is in place (similar to our East Fremont MOU) detailing the financials and who is doing what and when. |
||||||||||
3.D. North Bend Drainage District
Rationale:
Larry requested staff pass along a thank you. "We really appreciated all the help!"
|
||||||||||
4. SHELL CREEK WATERSHED
|
||||||||||
4.A. Shell Creek Implementation - 319 & NET
Rationale:
A SCWIC meeting occurred on 1/21 in Columbus, topics of discussion:
Bill submitted two applications for onsite wastewater upgrades:
|
||||||||||
5. WAHOO CREEK WATERSHED
|
||||||||||
5.A. WCW Construction Update
Rationale:
Update meeting was held 1/28, agenda attached. Highlights:
Latest invoice from TCI attached
Attachments:
(
)
|
||||||||||
5.B. Dam Site Planning Update
|
||||||||||
5.B.1. Design - Olsson
Rationale:
Site 77 re-design reached point we were able initiate landowner meetings.
Olsson, NRCS, and NRD staff will be meeting next week to plan construction timeline for next 6 sites. Permitting application for next 6 sites progressing as expected. Attached is the Progress Reports for the Wahoo Creek Watershed Dams and the invoice for the 2nd seven dams (55, 66, 77, 82, 84, 85, & 86; A18-3423). Olsson won’t have an invoice for the 1st three dams (26a, 26b, and 27). Their accounting department made some changes that didn’t get through in time, so they will send that invoice during the next cycle.
Attachments:
(
)
|
||||||||||
5.B.2. Real Estate - Olsson & Great Plains Appraisal
Rationale:
Cody Gerdes expects to have appraisal for site 84 to the NRD before February 10 Board meeting.
Danielle Allen will be present at Board meeting, a summary of work completed:
A motion from the floor will be required at Board Meeting. "To authorize Chair Sabatka to sign a purchase agreement with ______ for an easement on Wahoo Creek Site __." |
||||||||||
5.B.3. Funding - NRCS WFPO & NeDNR JEDI
Rationale:
Starting FY26, 7/1/25, our JEDI funding will have a $5 million/FY cap on spending until the funds are depleted. No other changes to the allocation are expected.
Our $1.35 million RCPP/WFPO construction fund for the first 3 sites is secure as of 1/29/25. |
||||||||||
5.C. Water Quality - NWQI & 319
Rationale:
NRCS is organizing the annual agency meeting. Staff will look at resurrecting the stakeholder group as we prepare the Section 319 grant applicaiton.
|
||||||||||
6. LOWER PLATTE RIVER CORRIDOR ALLIANCE
|
||||||||||
7. MORSE BLUFF LEVEE
Rationale:
There are signals from the legislature that funding may be appropriated through the JEDI. Staff are investigating.
|
||||||||||
8. EROSION AND SEDIMENT RULES AND REGULATIONS
|
||||||||||
9. HAZARD MITIGATION PLAN UPDATE
Rationale:
Round 2 of the public meetings were held in January. JEO will be reaching out to jurisdictions who have not returned their worksheets. They will be focusing on the development of the hazard mitigation plan in the next few months with a goal to have the plan out for public review in April.
For the Drought Mitigation Plan, we have met with 5 communities so far. There are 10 more scheduled with 3 more communities confirming dates to meet. The remaining 2 communities have been contacted, but have not reached back out. We will continue to reach out to these communities as we are planning to have all these meetings wrapped up by late February with the last of these meetings currently scheduled for February 20th. Attached find the current invoice from JEO for $21,549.50.
Attachments:
(
)
|
||||||||||
10. OTHER
Rationale:
The NRD was unsuccessful with the rail-on-trail ATIIP grant we sponsored on behalf of the Nebraska Trails Foundation.
|
||||||||||
11. ADJOURNMENT
|