June 23, 2016 at 8:30 AM - Regular Commission Meeting
| Agenda | 
|---|
| 
                    
                                        1. CALL TO ORDER/QUORUM                  | 
| 
                    
                                        2. PLEDGE OF ALLEGIANCE                  | 
| 
                    
                                        3. INVOCATION                 | 
| 
                    
                                        4. PUBLIC COMMENTS                  | 
| 
                    
                                        5. APPROVAL OF MINUTES                  | 
| 
                    
                                        6. APPROVAL OF TRAVEL                 | 
| 
                    
                                        7. FINANCIAL REPORT - MARY BOURDIN | 
| 
                    
                                        7.A. DISBURSEMENTS  | 
| 
                    
                                        7.B. LICENSES | 
| 
                    
                                        7.C. PROGRESS PAYMENTS | 
| 
                    
                                        7.C.1. BALCH & BINGHAM,LLP/14-FD-08 
        Description: 
RESTORATION ACTIVITIES - $ 1,156.25 GENERAL LEGAL SERVICES - $ 8,448.35 SOUTHERN INDUSTRIAL CONTRACTORS - $ 3,339.25 W C FORE TRUCKING APPEAL - $ 19,832.71 TOTAL BALCH & BINGHAM - $ 32,776.56 | 
| 
                    
                                        7.C.2. BROWN, MITCHELL & ALEXANDER, INC./13-EN-02 
        Description: 
GENERAL ENGINEERING - TASK 1 - $ 692.00 BULK HANDLING FACILITY – TASK 5 - $ 97,276.04 BERTH 7 DREDGE - TASK 6 - $ 3,470.75 BERTH 7 FENDER REPLACEMENT - TASK 8 - $ 2,649.00 TOTAL BMA - $ 104,087.79 | 
| 
                    
                                        7.C.3. CAN'T BE BEAT FENCE CO., LLC/14-EN-05 
        Description: 
TEMPORARY FENCING - BERTH 4 - $ 8,854.61 | 
| 
                    
                                        7.C.4. CONTINENTAL CONSTRUCTION CO., INC/15-EN-02 
        Description: 
BULK HANDLING FACILITY  - SILO PACKAGE – $ 38,239.74 | 
| 
                    
                                        7.C.5. DOLEAC ELECTRIC CO., INC/15-EN-08 
        Description: 
BULK HANDLING FACILITY - $ 1,413,488.85 | 
| 
                    
                                        7.C.6. G.A. WEST & CO., INC./15-EN-03 
        Description: 
BULK HANDLING FACILITY - CONVEYOR PACKAGE - $ 2,642,584.30 | 
| 
                    
                                        7.C.7. PRISM SYSTEMS, INC./15-EN-01 
        Description: 
BULK HANDLING FACILITY - CONTROL SYSTEM - $28,285.00 | 
| 
                    
                                        7.C.8. QES, INC./13-EN-03 
        Description: 
BULK HANDLING FACILITY - MATERIALS TESTING - $ 2,094.50  | 
| 
                    
                                        7.C.9. YATES ANDERSON JOINT VENTURE/14-EN-07 
        Description: 
BULK HANDLING FACILITY CM - $307,871.30 | 
| 
                    
                                        7.D. REQUESTS FOR CASH  | 
| 
                    
                                        7.D.1. AUTHORIZATION TO RESCIND RFC#126, APPROVED ON MAY 26, 2016 | 
| 
                    
                                        7.D.2. APPROVAL TO AMEND RFC #127 AND #128 | 
| 
                    
                                        7.D.3. RESTORATION AGREEMENT RFC #128                 
        Description: 
 THOMPSON ENGINEERING - $ 15,936.64 NEEL-SCHAFFER - $ 205,637.55 ATWELL & GENT - $ 47,550.30 ANCHOR QEA - $ 14,275.85 ATKINS - $ 37,831.41 CDM - $ 20,649.44 QES - $ 68,229.91 MICHAEL BAKER - $ 22,182.34 CH2M HILL - $ 248,114.37 WHARTON SMITH - $ 283,307.34 YATES ANDERSON JOINT VENTURE - $ 270,739.50 RFB, LLC - $5,291.25 TOTAL REQUEST FOR CASH #128 - $ 1,239,745.90 | 
| 
                    
                                        7.D.4. RESTORATION AGREEMENT RFC #129                 
        Description: 
 DAN HENSARLING - $ 211,764.50 NECAISE BROTHERS - $ 2,728,193.21 MSPA - $ 70,498.38 TOTAL REQUEST FOR CASH #129 - $ 3,010,456.09 | 
| 
                    
                                        7.D.5. RESTORATION AGREEMENT RFC #130                 
        Description: 
 SOUTHERN INDUSTRIAL CONTRACTORS - $ 4,475,125.09 L&A CONTRACTING CO., INC - $ 449,654.41 ANCHOR QEA - $ 30,446.15 TOTAL REQUEST FOR CASH # 130 - $ 4,955,225.65 | 
| 
                    
                                        7.E. CDBG PROGRESS PAYMENTS | 
| 
                    
                                        7.E.1. HOLDEN EARTH MOVING & CONSTRUCTION CO., INC. - $ 225,195.00 | 
| 
                    
                                        7.E.2. J. LEVENS BUILDERS, INC. - $ 97,701.72 | 
| 
                    
                                        8. OLD BUSINESS | 
| 
                    
                                        8.A. (JW)  APPROVAL OF A NOTICE OF COMPLETION WITH CONTINENTAL CONSTRUCTION CO. UNDER CONTRACT NO. 15-EN-02 | 
| 
                    
                                        8.B. (JW)  APPROVAL OF AMENDMENT NO. 3 TO TASK ORDER NO. 28 WITH NEEL SCHAFFER, INC. UNDER CONTRACT 010-HUD-001 | 
| 
                    
                                        8.C. (JW)  APPROVAL OF AMENDMENT NO. 2 TO TASK ORDER NO. 29 WITH NEEL SCHAFFER, INC. UNDER CONTRACT 010-HUD-001 | 
| 
                    
                                        8.D. (JW)  APPROVAL OF AMENDMENT NO. 5 TO TASK ORDER NO. 32 WITH NEEL SCHAFFER, INC. UNDER CONTRACT 010-HUD-001 | 
| 
                    
                                        8.E. (NF)  APPROVAL OF AMENDMENT NO. 4 TO TASK ORDER NO. 15 WITH ANCHOR QEA, LLC UNDER CONTRACT NO. 010-HUD-011 | 
| 
                    
                                        8.F. (NF)  AUTHORIZATION TO AWARD A CONTRACT FOR THE TERMINAL 2 M&R PROJECT | 
| 
                    
                                        8.G. (NF)  APPROVAL OF AMENDMENT NO. 5 TO TASK ORDER NO. 8 WITH ATWELL & GENT UNDER CONTRACT NO. 010-HUD-013 | 
| 
                    
                                        9. NEW BUSINESS | 
| 
                    
                                        9.A. (MB)  APPROVAL OF FY17 OPERATING BUDGET | 
| 
                    
                                        9.B. (DW)  APPROVAL OF PROPOSED CHANGES TO TERMINAL TARIFF #6 | 
| 
                    
                                        9.C. (JW)  APPROVAL OF TASK ORDER NO. 43 WITH NEEL SCHAFFER, INC. UNDER CONTRACT NO. 010-HUD-001 | 
| 
                    
                                        9.D. (NF)  APPROVAL OF TASK ORDER NO. 14 WITH QES, INC. UNDER CONTRACT NO. 010-HUD-003 | 
| 
                    
                                        9.E. (NF)  APPROVAL OF TASK ORDER NO. 15 WITH QES, INC. UNDER CONTRACT NO. 010-HUD-003 | 
| 
                    
                                        10. PORT RESTORATION UPDATE  - NICK FOTO                 | 
| 
                    
                                        11. OPERATIONS REPORT - MATTHEW WYPYSKI                 | 
| 
                    
                                        12. EXECUTIVE DIRECTOR’S REPORT - JONATHAN DANIELS                 | 
| 
                    
                                        13. GENERAL COUNSEL’S COMMENTS                 | 
| 
                    
                                        14. MDA COMMENTS                 | 
| 
                    
                                        15. COMMISSIONER COMMENTS                  | 
| 
                    
                                        16.  EXECUTIVE SESSION - LEASE NEGOTIATIONS                 | 
| 
                    
                                        17. ADJOURNMENT                 |