April 20, 2016 at 8:30 AM - Regular Commission Meeting
Agenda |
---|
1. CALL TO ORDER/QUORUM
|
2. PLEDGE OF ALLEGIANCE
|
3. PUBLIC COMMENTS
|
4. APPROVAL OF MINUTES
|
5. APPROVAL OF TRAVEL
|
6. FINANCIAL REPORT - MARY BOURDIN
|
6.A. DISBURSEMENTS
|
6.B. LICENSES
|
6.C. PROGRESS PAYMENTS
|
6.C.1. BALCH & BINGHAM,LLP/14-FD-08
Description:
GENERAL LEGAL SERVICES - $ 21,855.68
RESTORATION ACTIVITIES - $ 6,752.03 SOUTHERN INDUSTRIAL CONTRACTORS - $ 2,543.75 W C FORE TRUCKING APPEAL - $ 21,792.00 TOTAL BALCH & BINGHAM - $ 52,943.46 |
6.C.2. BROWN, MITCHELL & ALEXANDER, INC./13-EN-02
Description:
GENERAL ENGINEERING - TASK 1 - $ 2,872.50
BULK HANDLING FACILITY – TASK 5 - $ 85,751.44 BERTH 7 DREDGE - TASK 6 - $ 1,378.00 TOTAL BMA - $ 90,001.94 |
6.C.3. CONTINENTAL CONSTRUCTION CO., INC/15-EN-02
Description:
BULK HANDLING FACILITY - SILO PACKAGE – $316,207.50
|
6.C.4. DOLEAC ELECTRIC CO.,INC./15-EN-08
Description:
BULK HANDLING FACILITY - $91,867.85
|
6.C.5. G.A. WEST & CO., INC./15-EN-03
Description:
BULK HANDLING FACILITY - CONVEYOR PACKAGE – $1,860,394.84
|
6.C.6. QES, INC./13-EN-03
Description:
BULK HANDLING FACILITY - MATERIALS TESTING - $ 4,254.00
|
6.C.7. YATES ANDERSON JOINT VENTURE/14-EN-07
Description:
BULK HANDLING FACILITY CM - $231,945.91
|
6.C.8. ZPMC, LTD/ 15-EN-07
Description:
TRAVELING HOPPER - $ 192,000.00
|
6.D. REQUESTS FOR CASH
|
6.D.1. RESTORATION AGREEMENT RFC #120
Description:
THOMPSON ENGINEERING - $ 16,676.16 NEEL-SCHAFFER - $ 176,326.44 ATWELL & GENT - $ 16,254.84 ANCHOR QEA - $ 39,185.26 ATKINS - $ 33,986.81 QES - $ 68,814.41 MSPA - $ 118,739.34 MICHAEL BAKER - $ 9,736.43 CDM - $ 79,684.83 RFB, INC - $ 3,846.25 YATES ANDERSON JOINT VENTURE - $ 495,092.00 DAN HENSARLING - $ 239,016.20 WHARTON SMITH - $ 61,919.10 RESTORATION AGREEMENT RFC #116 SUBTOTAL - $ 1,359,278.07 |
6.D.2. RESTORATION AGREEMENT RFC #121
Description:
NECAISE BROTHERS - $ 4,978,790.30 |
6.D.3. RESTORATION AGREEMENT RFC #122
Description:
L&A CONTRACTORS - $ 1,008,412.25 RFB, LLC - $ 3,315.00 TOTAL REQUEST FOR CASH #122 - $ 1,011,727.25 |
6.E. FOR SEPARATE APPROVAL
|
6.E.1. FROM RESTORATION AGREEMENT REQUEST #120:
CH2M HILL - $208,585.61 |
6.E.2. FROM RESTORATION AGREEMENT REQUEST #120
ELEY, GUILD, HARDY - $ 44,208.50 TOTAL REQUEST FOR CASH #120 - $ 1,612,072.18 |
7. OLD BUSINESS
|
7.A. (NF) APPROVAL OF AMENDMENT NO. 1 TO CONTRACT NO. 013-HUD-017 WITH RFB, LLC
|
7.B. (JW) AUTHORIZATION TO ADVERTISE FOR BID THE BERTH 7 FENDER REPLACEMENT PROJECT
|
7.C. (JW) AUTHORIZATION TO ADVERTISE FOR BID THE BERTH 7 DREDGING PROJECT
|
7.D. (NF) APPROVAL OF AMENDMENT NO. 4 TO TASK ORDER NO. 21 WITH NEEL-SCHAFFER, INC. UNDER CONTRACT NO. 010-HUD-001
|
7.E. (NF) APPROVAL OF AMENDMENT NO. 7 TO TASK ORDER NO. 22 WITH NEEL-SCHAFFER, INC. UNDER CONTRACT NO. 010-HUD-001
|
7.F. (NF) APPROVAL OF AMENDMENT NO. 2 TO TASK ORDER NO. 18 WITH THOMPSON ENGINEERING UNDER CONTRACT NO. 010-HUD-002
|
7.G. (NF) APPROVAL OF AMENDMENT NO. 3 TO TASK ORDER NO. 6 WITH QES, INC. UNDER CONTRACT NO. 010-HUD-003
|
7.H. (NF) APPROVAL OF AMENDMENT NO. 1 TO TASK ORDER NO. 10 WITH QES, INC. UNDER CONTRACT NO. 010-HUD-003
|
7.I. (JW) APPROVAL OF AMENDMENT NO. 1 TO TASK ORDER NO. 12 WITH QES, INC. UNDER CONTRACT NO. 010-HUD-003
|
7.J. (JW) APPROVAL OF AMENDMENT NO. 3 TO TASK ORDER NO. 9 WITH YAJV UNDER CONTRACT NO. 010-HUD-006
|
7.K. (JW) APPROVAL OF AMENDMENT NO. 1 TO TASK ORDER NO. 17 WITH YAJV UNDER CONTRACT NO. 010-HUD-006
|
7.L. (NF) APPROVAL OF AMENDMENT NO. 1 TO TASK ORDER NO. 12 WITH VOLKERT,INC. UNDER CONTRACT NO. 010-HUD-007
|
7.M. (NF) APPROVAL OF AMENDMENT NO. 2 WITH TASK ORDER NO. 13 WITH ANCHOR QEA, LLC UNDER CONTRACT NO. 010-HUD-011
|
7.N. (NF) APPROVAL OF AMENDMENT NO. 4 TO TASK ORDER NO. 20 WITH ANCHOR QEA, LLC UNDER CONTRACT NO. 010-HUD-011
|
7.O. (JW) APPROVAL OF AMENDMENT NO. 5 TO TASK ORDER NO. 2 WITH ATWELL & GENT, P.A. UNDER CONTRACT NO. 010-HUD-013
|
7.P. (NF) APPROVAL OF CHANGE ORDER NO. 2 TO SOUTHERN INDUSTRIAL CONTRACTORS UNDER CONTRACT NO. 015-HUD-025
|
7.Q. (NF) APPROVAL OF CHANGE ORDER NO. 11 TO L&A CONTRACTING UNDER CONTRACT NO. 013-HUD-018
|
7.R. (NF) APPROVAL OF CHANGE ORDER NO. 7 TO NECAISE BROTHERS CONSTRUCTION UNDER CONTRACT NO. 015-HUD-026
|
7.S. (NF) APPROVAL OF CHANGE ORDER NO. 4 TO DAN HENSARLING, INC. UNDER CONTRACT NO. 015-HUD-029
|
7.T. (MW) APPROVAL OF AMENDMENT NO. 2 TO THE TERMINAL OPERATING AGREEMENT AND SPACE ASSIGNMENT WITH CROWLEY LATIN AMERICA SERVICES, INC.
|
8. NEW BUSINESS
|
8.A. (JD) APPROVAL OF RESOLUTION NO. 16-03 REGARDING THE LEASEHOLD DEED OF TRUST RELATIVE TO THE MCDERMOTT, INC. LEASE
|
9. PORT RESTORATION UPDATE - NICK FOTO
|
10. OPERATIONS REPORT - MATTHEW WYPYSKI
|
11. STATUS REPORT ON THE ENVIRONMENTAL IMPACT STATEMENT - ELIZABETH CALVIT, CH2MHILL
|
12. EXECUTIVE DIRECTOR’S REPORT - JONATHAN DANIELS
|
13. GENERAL COUNSEL’S COMMENTS
|
14. MDA COMMENTS
|
15. COMMISSIONER COMMENTS
|
16. EXECUTIVE SESSION - LEGAL MATTERS (LITIGATION)
|
17. ADJOURNMENT
|