June 13, 2013 at 8:30 AM - Regular Meeting
| Agenda | 
|---|
| 
                    
                                        1. CALL TO ORDER/QUORUM - COMMISSIONER SIMPSON                 | 
| 
                    
                                        2. PLEDGE OF ALLEGIANCE - COMMISSIONER SIMPSON                 | 
| 
                    
                                        3. PUBLIC COMMENTS - AUDIENCE                 | 
| 
                    
                                        4. APPROVAL OF MINUTES                  | 
| 
                    
                                        5. APPROVAL OF TRAVEL                 | 
| 
                    
                                        6. FINANCIAL REPORT - MARY BOURDIN                 | 
| 
                    
                                        6.A. DISBURSEMENTS                 | 
| 
                    
                                        6.B. REQUEST FOR CASH - RESTORATION AGREEMENT REQUEST #55 
        Description: 
MSPA - $ 97,534.49  RFB, LLC - $ 5,525.00 ARCHER WESTERN - $ 5,022,410.21 NEEL SCHAFFER - $ 218,475.93 QES - $ 5,605.00 THOMPSON ENGINEERING - $ 13.769.70 ATWELL & GENT - $ 65,876.12 ATKINS - $ 46,078.93 ANCHOR QEA - $ 198,231.75 CH2M HILL - $ 271,454.32 SUB-TOTAL RESTORATION AGREEMENT #55 $ 5,944,961.45 | 
| 
                    
                                        6.C. PROGRESS PAYMENTS | 
| 
                    
                                        6.C.1. BROWN, MITCHELL & ALEXANDER, INC./13-EN-02 
        Description: 
GENERAL ENGINEERING - TASK 1 -  $ 136.50 SECURITY GATE CM – TASK 2 - $ 8,267.75 ILMENITE FACILITY – TASK 3 - $ 8,891.22 SHED 50 RAIL EXPANSION - TASK 4- $ 11,534.45 TOTAL BMA - $28,919.82 | 
| 
                    
                                        6.C.2. BMI ENVIRONMENTAL SERVICES/09-EN-03 
        Description: 
WATER QUALITY MONITORING – TASK 1 -  $ 317.50 MITIGATION ACTIVITIES 84 ACRES - TASK 2 - $ 115.00 TOTAL BMI - $ 432.50 | 
| 
                    
                                        6.C.3. QES, INC./13-EN-03 
        Description: 
SECURITY GATE COMPLEX - $ 3,258.00 CROWLEY M&R AND TIRE - $ 105.00 TOTAL QES - $ 3,363.00 | 
| 
                    
                                        6.C.4. ROD COOKE CONSTRUCTION CO./13-EN-01                  
        Description: 
SECURITY GATE -  $ 202,727.30 CROWLEY M & R AND TIRE SHOP - $19,305.90 TOTAL ROD COOKE - $ 222,033.20 | 
| 
                    
                                        6.D. FOR SEPARATE APPROVAL | 
| 
                    
                                        6.D.1. BALCH & BINGHAM, LLP/11-FD-02                 
        Description: 
GENERAL LEGAL SERVICES -  $ 22,453.22 RESTORATION ACTIVITIES - $ 20,288.41 TOTAL BALCH & BINGHAM - $ 42,741.63 | 
| 
                    
                                        6.D.2. YATES & ANDERSON JV - RFC #55 - $ 157,751.09                 
        Description: 
TOTAL REQUEST FOR CASH #55 (FROM 6B) -  $ 6,102,712.54 | 
| 
                    
                                        7. OLD BUSINESS | 
| 
                    
                                        7.A. APPROVAL OF MODIFICATION NO. 3 TO CONTRACT NO. 09-EN-03; BMI ENVIRONMENTAL SERVICES, LLC | 
| 
                    
                                        7.B. AUTHORIZATION TO AWARD THE PURCHASE OF A FORKLIFT | 
| 
                    
                                        7.C. APPROVAL OF MODIFICATION NO. 1 TO CONTRACT NO. 11-FD-04; RICK MALDONADO & ASSOCIATES, INC. | 
| 
                    
                                        7.D. APPROVAL OF AMENDMENT NO. 2 TO TASK ORDER NO. 11; CONTRACT NO. 010-HUD-002; THOMPSON ENGINEERING (GEOTECHNICAL DESIGN) | 
| 
                    
                                        7.E. APPROVAL OF AMENDMENT NO. 2 TO TASK ORDER NO. 8; CONTRACT NO. 010-HUD-007; VOLKERT, INC. (ENVIRONMENTAL SERVICES) | 
| 
                    
                                        7.F. APPROVAL OF AMENDMENT NO. 3 TO TASK ORDER NO. 2; CONTRACT NO. 010-HUD-010; MICHAEL BAKER, JR., INC. (COASTAL ENGINEERING DESIGN) | 
| 
                    
                                        7.G. APPROVAL OF CHANGE ORDER NO. 9 TO CONTRACT NO. 012-HUD-016; ARCHER WESTERN (24 ACRE DREDGE & FILL) | 
| 
                    
                                        7.H. CONSIDERATION OF STONE COUNTY'S REQUEST FOR COMPENSATION REGARDING ROAD CONDITIONS | 
| 
                    
                                        8. NEW BUSINESS | 
| 
                    
                                        8.A. APPROVAL OF FY14 OPERATING BUDGET | 
| 
                    
                                        8.B. APPROVAL OF RESOLUTION NO. 13-02 RE: BANK SIGNATURES | 
| 
                    
                                        8.C. APPROVAL OF TASK ORDER NO. 24 UNDER CONTRACT NO. 010-HUD-001; NEEL SCHAFFER (GENERAL ENGINEERING & DESIGN) | 
| 
                    
                                        8.D. APPROVAL OF TASK ORDER NO. 10 UNDER CONTRACT NO. 010-HUD-007; VOLKERT, INC. (ENVIRONMENTAL SERVICES) | 
| 
                    
                                        8.E. AUTHORIZATION TO PURCHASE THREE (3) CRANES FOR THE WEST PIER | 
| 
                    
                                        8.F. APPROVAL OF TASK ORDER NO. 11 TO CONTRACT NO. 010-HUD--006; YATES ANDERSON JV (CONSTRUCTION MANAGEMENT) | 
| 
                    
                                        9.    PORT RESTORATION UPDATE  - JOE CONN                 | 
| 
                    
                                        10. EXECUTIVE DIRECTOR’S REPORT - JONATHAN DANIELS                 | 
| 
                    
                                        11. GENERAL COUNSEL’S COMMENTS - BALCH & BINGHAM                 | 
| 
                    
                                        12. MDA’S COMMENTS                 | 
| 
                    
                                        13. COMMISSIONERS’ COMMENTS                  | 
| 
                    
                                        14. COMMUNICATIONS - THE GIBBES CO.                 | 
| 
                    
                                        15.  EXECUTIVE SESSION (Legal, Real Estate and Personnel)                 | 
| 
                    
                                        16. ADJOURNMENT                 |