June 2, 2021 at 7:00 AM - Buildings & Sites Committee Meeting
Agenda |
---|
I. Call to Order
|
II. Discussion Items
|
II.A. Lost Time - Overtime Report
Discussion:
The attached report covers timecards from 5/1 through 5/25. Significant OT was required to cover at Ross. 2 custodians off on extended medical or workman comp leave. We also covered the .5FTE position at Admin/Mac until our new hire started on 5/18.
Attachments:
(
)
|
II.B. Discussion of Summer 2021 Work
Discussion:
The attached file provides a financial overview of the capital projects for Summer 2021. Column D represents pay requests that have been submitted, reviewed, and approved for payment. These pay requests, will be an action item for the June Board meeting.
HVAC Project- Honeywell is completing engineering drawings. EMCOR has prepared construction schedule and is under review. Start date is week of June 7th. All equipment and material is on-hand in EMCOR's shop (BSR confirmed) Roofing Project - On May 24th we have been notified by the roofing contractor that building material manufacturers for insulation are now experiencing shortages and delays. ARCON is working with manufacturer, distributor, and contractor to determine impact. This is an industry/country wide issue at this point in time.
Attachments:
(
)
|
II.C. Bond & Capital Grant Update
Discussion:
The bonds are scheduled to close next week with funds posting to the District's account on June 9th. Chapman and Cutler is in the process of preparing the transfer resolution for Board approval at the June 9th meeting. We will receive the resolution early next week and will share it with the Committee at our upcoming meeting. We will be moving the bond proceeds from the Working Cash fund into Operations and Maintenance and then to Capital Projects for project scheduling and payment.
|
II.D. FY22 Furniture Updates
Discussion:
In accordance with our ongoing plan to address furniture replacements at each building, the FY22 Budgetary Guidelines articulated the need for the continued allocation of funds through two non-discretionary line items. An update on those purchases has been attached for the Committee's review.
Attachments:
(
)
|
II.E. Plan for Classroom Furniture Movement back into Buildings
Discussion:
PODS will be scheduled for delivery to IKE, ROSS, and SULL mid-July. MAC furniture is located onsite. Custodial, maintenance, and summer worker staff will clean and move furniture back into designated classrooms.
|
II.F. Summer Custodial Work
Discussion:
10 summer workers have been hired. Their orientation and start date is Monday June 7th. All custodial vacation time and work hours have been finalized/organized. Most of our custodians elect to work 4 x 10 hr days, and many night custodians adjust their hours to "day" hours, the custodians appreciate this summer program opportunity. Marcus and Brian reviewed the VCT (floor tile) District wide and developed an action plan for the custodians. Many of the floors are still in great condition due to less foot traffic (COVID), and will require less maintenance this summer.
|
III. Old Business
|
III.A. Approval of Minutes - Buildings & Sites Committee Meeting of April 6, 2021
Discussion:
The Buildings & Sites Committee recommends the approval of the minutes of the April 6, 2021 meeting as attached.
Attachments:
(
)
|
IV. New Business
|
V. Adjournment
|